(0-2MFT)SCR
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Curnyn Construction Co. Low bidder | $73,844 | ||
| 2 | Miller Trucking & Excavating Company | $78,271 | +6.0% | |
| 3 | Phoenix Corporation of the Quad Cities | $80,992 | +9.7% | |
| 4 | Brandt Construction Co. | $83,908 | +13.6% | |
| 5 | Fischer Excavating, Inc. | $84,272 | +14.1% | |
| 6 | Martin & Company Excavating | $85,500 | +15.8% | |
| 7 | O'Brien Civil Works, Inc. | $119,495 | +61.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Curnyn Construc… | #2 Miller Trucking… | #3 Phoenix Corpora… | #4 Brandt Construc… | #5 Fischer Excavat… | #6 Martin & Compan… | #7 O'Brien Civil W… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0005300 | BOX CUL TO BE CLEANED | 1 | EACH | $8,500.00 | $5,000.00 | $5,500.00 | $22,000.00 | $10,500.00 | $11,500.00 | $15,400.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,200.00 | $2,800.00 | $3,000.00 | $2,700.00 | $3,800.00 | $1,250.00 | $3,000.00 | |
| 3 | Z0025505 | PROPERTY MARKERS | 1 | EACH | $275.00 | $650.00 | $650.00 | $625.00 | $1,500.00 | $250.00 | $640.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 820 | CU YD | $25.00 | $22.00 | $23.50 | $20.00 | $24.00 | $32.00 | $38.50 | |
| 5 | 21400100 | GRADING & SHAP DITCH | 75 | FOOT | $15.00 | $35.00 | $20.00 | $15.00 | $17.00 | $31.00 | $40.00 | |
| 6 | 25100630 | EROSION CONTR BLANKET | 1,538 | SQ YD | $1.50 | $3.50 | $3.00 | $3.50 | $1.25 | $4.00 | $3.85 | |
| 7 | 28000250 | TEMP EROS CONTR SEED | 127 | POUND | $4.00 | $5.00 | $3.00 | $5.00 | $10.00 | $1.00 | $5.00 | |
| 8 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $225.00 | $275.00 | $150.00 | $175.00 | $200.00 | $220.00 | $500.00 | |
| 9 | 28100107 | STONE RIPRAP CL A4 | 478 | SQ YD | $40.00 | $65.00 | $73.00 | $47.00 | $61.00 | $48.33 | $90.00 | |
| 10 | 28200200 | FILTER FABRIC | 478 | SQ YD | $3.00 | $3.75 | $1.00 | $3.00 | $2.00 | $3.00 | $3.00 | |
| 11 | 60100925 | PIPE DRAINS 8 | 20 | FOOT | $30.00 | $50.00 | $12.75 | $30.00 | $63.00 | $40.00 | $90.00 | |
| 12 | 61133200 | FLD TILE JUN VAULT 3D | 1 | EACH | $1,800.00 | $1,750.00 | $150.00 | $800.00 | $3,250.00 | $2,800.00 | $2,500.00 | |
| 13 | 66600105 | FUR ERECT ROW MARKERS | 5 | EACH | $250.00 | $350.00 | $400.00 | $350.00 | $400.00 | $300.00 | $340.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $4,000.00 | $2,500.00 | $5,400.00 | $4,500.00 | $5,000.00 | $4,800.00 | $5,500.00 | |
| 15 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $10,000.00 | $3,000.00 | $2,750.00 | $3,315.00 | $2,500.00 | $3,000.00 | $2,875.00 |