101RS-4
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $931,757 | ||
| 2 | Valley Construction Co. | $949,756 | +1.9% | |
| 3 | Brandt Construction Co. | $1,165,770 | +25.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… | #2 Valley Construc… | #3 Brandt Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0004542 | HMA REMOVAL SPL | 993 | SQ YD | $13.00 | $12.00 | $15.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $11,895.00 | $2,450.00 | $4,000.00 | |
| 3 | Z0025505 | PROPERTY MARKERS | 5 | EACH | $407.00 | $190.00 | $140.00 | |
| 4 | Z0033700 | LONG JOINT SEALANT | 8,930 | FOOT | $2.10 | $2.00 | $2.50 | |
| 5 | 20200100 | EARTH EXCAVATION | 15 | CU YD | $80.00 | $110.00 | $40.00 | |
| 6 | 21101615 | TOPSOIL F & P 4 | 115 | SQ YD | $20.00 | $10.00 | $20.00 | |
| 7 | 25200110 | SODDING SALT TOLERANT | 115 | SQ YD | $75.00 | $50.00 | $45.00 | |
| 8 | 25200200 | SUPPLE WATERING | 4 | UNIT | $200.00 | $20.00 | $225.00 | |
| 9 | 28000250 | TEMP EROS CONTR SEED | 24 | POUND | $5.00 | $2.00 | $6.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 18,260 | POUND | $0.6500 | $0.1000 | $3.00 | |
| 11 | 40600990 | TEMPORARY RAMP | 491 | SQ YD | $7.50 | $15.00 | $28.00 | |
| 12 | 40601005 | HMA REPL OVER PATCH | 392 | TON | $120.00 | $128.00 | $150.00 | |
| 13 | 40602978 | HMA BC IL-9.5 N50 | 3,334 | TON | $72.00 | $73.00 | $70.00 | |
| 14 | 40604050 | HMA SC IL-9.5 C N50 | 3,418 | TON | $72.00 | $73.00 | $80.00 | |
| 15 | 40800050 | INCIDENTAL HMA SURF | 193 | TON | $125.00 | $140.00 | $180.00 | |
| 16 | 42300300 | PCC DRIVEWAY PAVT 7 | 374 | SQ YD | $67.50 | $77.00 | $70.00 | |
| 17 | 42400200 | PC CONC SIDEWALK 5 | 410 | SQ FT | $16.90 | $18.00 | $16.00 | |
| 18 | 42400800 | DETECTABLE WARNINGS | 30 | SQ FT | $29.00 | $30.00 | $28.50 | |
| 19 | 44000155 | HMA SURF REM 1 1/2 | 15,876 | SQ YD | $1.60 | $1.85 | $2.50 | |
| 20 | 44000158 | HMA SURF REM 2 1/4 | 2,101 | SQ YD | $6.10 | $10.00 | $12.00 | |
| 21 | 44000164 | HMA SURF REM 3 3/4 | 23,814 | SQ YD | $2.75 | $2.85 | $4.00 | |
| 22 | 44000200 | DRIVE PAVEMENT REM | 374 | SQ YD | $9.00 | $17.00 | $18.00 | |
| 23 | 44000500 | COMB CURB GUTTER REM | 116 | FOOT | $15.00 | $18.00 | $15.00 | |
| 24 | 44000600 | SIDEWALK REM | 355 | SQ FT | $3.25 | $3.00 | $3.00 | |
| 25 | 44002235 | HMA RM OV PATCH 8 3/4 | 800 | SQ YD | $27.00 | $22.00 | $85.00 | |
| 26 | 44300200 | STRIP REF CR CON TR | 17,860 | FOOT | $0.8500 | $0.8000 | $0.9500 | |
| 27 | 48102100 | AGG WEDGE SHLD TYPE B | 1,018 | TON | $20.00 | $25.00 | $25.00 | |
| 28 | 542D0220 | P CUL CL D 1 15 | 94 | FOOT | $57.00 | $60.00 | $52.00 | |
| 29 | 54260515 | SLOP MET ES 15", 1:6 | 2 | EACH | $1,315.00 | $1,000.00 | $700.00 | |
| 30 | 60605000 | COMB CC&G TB6.24 | 118 | FOOT | $65.00 | $64.00 | $75.00 | |
| 31 | 64200116 | SHOULDER RUM STRIP 16 | 15,860 | FOOT | $0.7000 | $0.8500 | $0.6500 | |
| 32 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $2,250.00 | $1,500.00 | $2,500.00 | |
| 33 | 67100100 | MOBILIZATION | 1 | L SUM | $43,000.00 | $53,000.00 | $72,000.00 | |
| 34 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $4,000.00 | $100.00 | $115.00 | |
| 35 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $6,500.00 | $3,750.00 | $4,500.00 | |
| 36 | 70102621 | TR CONT & PROT 701501 | 1 | EACH | $2,500.00 | $2,500.00 | $3,000.00 | |
| 37 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $100.00 | $115.00 | |
| 38 | 70300100 | SHORT TERM PAVT MKING | 8,243 | FOOT | $0.4000 | $0.6000 | $0.7500 | |
| 39 | 70300150 | SHRT TRM PAVT MK REM | 916 | SQ FT | $1.00 | $2.00 | $6.00 | |
| 40 | 78001110 | PAINT PVT MK LINE 4 | 46,484 | FOOT | $0.1200 | $0.1300 | $0.1500 | |
| 41 | 78001130 | PAINT PVT MK LINE 6 | 82 | FOOT | $0.2500 | $1.00 | $0.5000 | |
| 42 | 78001180 | PAINT PVT MK LINE 24 | 229 | FOOT | $3.00 | $4.00 | $3.35 |