2023-SWP-003(NC)
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Central Sweeping of Illinois, LLC Low bidder | $2,653,175 | ||
| 2 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | $5,436,250 | +104.9% |
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Central Sweeping of Illinois, LLC Low bidder | $2,653,175 | ||
| 2 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | $5,436,250 | +104.9% |