2021-146-I
- Let date
- Friday, November 5, 2021
- Contract
- 62P62 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- (528-Mile) Litter/ Debris Removal from edge of pavement to the Pedestrian Barrier on 1) FAI 94: 1-94 from 1-90/94 (Dan Ryan Expwy) to 1-80; 2) FAP 341: Stony Island from 1-94 to US 12 (95th) 3) FAU 1574: 103rd St from Cottage Groove to Stony Island.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Peeples Landscaping and Snow Removal Ltd. Low bidder | $580,267 | ||
| 2 | MYS, Incorporated | $633,405 | +9.2% | |
| 3 | Vixen Construction, Inc. | $908,160 | +56.5% | |
| 4 | Scruggs Machinery Equipment Construction Commodity Co. | $1,372,800 | +136.6% |