2020-219-DM
- Let date
- Friday, March 5, 2021
- Contract
- 62M94 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- This work consists of building demolition located along Rand Road near the bridge over the Des Plaines River. This project has a gross length of 349 LF.
- Classification
- Building demolition located along Rand Road near the bridge over the Des Plaines River
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martam Construction Incorporated Low bidder | $173,405 | ||
| 2 | Copenhaver Construction, Inc. | $208,715 | +20.4% | |
| 3 | Campanella and Sons, Inc. | $223,067 | +28.6% | |
| 4 | MYS, Incorporated | $283,721 | +63.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martam Construc… | #2 Copenhaver Cons… | #3 Campanella and … | #4 MYS, Incorporat… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0840000 | SAN SEW REMOV 8 | 183 | FOOT | $30.00 | $40.00 | $16.68 | $50.00 | |
| 2 | X5620124 | WATER SERV LINE REM | 168 | FOOT | $30.00 | $35.00 | $20.24 | $100.00 | |
| 3 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $16,000.00 | $40,000.00 | $40,470.84 | $39,120.00 | |
| 4 | Z0007602 | BLDG REMOV NO 2 | 1 | L SUM | $22,200.00 | $40,000.00 | $37,215.98 | $32,520.00 | |
| 5 | Z0007603 | BLDG REMOV NO 3 | 1 | L SUM | $20,000.00 | $35,000.00 | $44,602.52 | $30,840.00 | |
| 6 | Z0015500 | DEBRIS REMOVAL | 1 | L SUM | $1,500.00 | $7,500.00 | $3,317.50 | $12,360.00 | |
| 7 | Z0022800 | FENCE REMOVAL | 559 | FOOT | $5.00 | $7.00 | $5.40 | $12.00 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 32 | SQ FT | $30.00 | $20.00 | $26.25 | $35.00 | |
| 9 | Z0049902 | R&D NON-FR ASB BLD 2 | 1 | L SUM | $20,000.00 | $15,000.00 | $11,686.50 | $25,000.00 | |
| 10 | Z0064800 | SELECTIVE CLEARING | 47 | UNIT | $100.00 | $30.00 | $262.50 | $350.00 | |
| 11 | Z0076600 | TRAINEES | 200 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 12 | Z0076604 | TRAINEES TPG | 200 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 13 | 20100110 | TREE REMOV 6-15 | 9 | UNIT | $100.00 | $40.00 | $15.75 | $34.00 | |
| 14 | 20100210 | TREE REMOV OVER 15 | 10 | UNIT | $120.00 | $230.00 | $19.95 | $43.00 | |
| 15 | 20101000 | TEMPORARY FENCE | 535 | FOOT | $10.00 | $9.00 | $2.10 | $5.00 | |
| 16 | 20101100 | TREE TRUNK PROTECTION | 6 | EACH | $150.00 | $100.00 | $105.00 | $92.00 | |
| 17 | 21101615 | TOPSOIL F & P 4 | 1,549 | SQ YD | $1.00 | $4.00 | $5.80 | $11.00 | |
| 18 | 25000200 | SEEDING CL 2 | 0.5 | ACRE | $22,000.00 | $2,500.00 | $2,415.00 | $2,500.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 30 | POUND | $2.00 | $1.00 | $2.10 | $4.00 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 30 | POUND | $2.00 | $1.00 | $2.10 | $4.00 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 30 | POUND | $2.00 | $1.00 | $2.10 | $4.00 | |
| 22 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $4,000.00 | $4,500.00 | $3,675.00 | $4,025.00 | |
| 23 | 28000400 | PERIMETER EROS BAR | 857 | FOOT | $3.00 | $3.00 | $3.15 | $4.00 | |
| 24 | 44000100 | PAVEMENT REM | 41 | SQ YD | $20.00 | $20.00 | $14.27 | $15.00 | |
| 25 | 44000200 | DRIVE PAVEMENT REM | 610 | SQ YD | $12.00 | $15.00 | $6.27 | $15.00 | |
| 26 | 44000600 | SIDEWALK REM | 235 | SQ FT | $2.00 | $4.00 | $2.49 | $5.00 | |
| 27 | 66901006 | REG SUB MON | 9 | CAL DA | $900.00 | $300.00 | $1,200.00 | $1,500.00 | |
| 28 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,200.00 | $500.00 | $3,500.00 | $2,000.00 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $11,850.00 | $6,157.00 | $26,000.00 |