2020-109-RS&SW
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $719,199 | ||
| 2 | K-Five Construction Corporation | $773,778 | +7.6% | |
| 3 | Builders Paving, LLC | $788,000 | +9.6% | |
| 4 | R. W. Dunteman Company | $798,785 | +11.1% | |
| 5 | J. A. Johnson Paving Company | $814,700 | +13.3% | |
| 6 | Lindahl Brothers, Inc. | $873,639 | +21.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 K-Five Construc… | #3 Builders Paving… | #4 R. W. Dunteman … | #5 J. A. Johnson P… | #6 Lindahl Brother… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $3,000.00 | $5,000.00 | $3,000.00 | $2,849.00 | $5,000.00 | $3,900.00 | |
| 2 | X0327611 | REM & REIN BRIC PAVER | 100 | SQ FT | $20.00 | $20.00 | $30.00 | $20.00 | $30.00 | $14.00 | |
| 3 | X4400501 | COMB C&G REMOV REPL < = 10FT | 700 | FOOT | $39.00 | $38.00 | $41.75 | $42.00 | $39.90 | $43.44 | |
| 4 | X5537800 | SS CLEANED 12 | 700 | FOOT | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $4.00 | |
| 5 | X6030310 | FR & LIDS ADJUST SPL | 35 | EACH | $625.00 | $650.00 | $650.00 | $700.00 | $650.00 | $650.00 | |
| 6 | X7030005 | TEMP PAVT MKING REMOV | 14,824 | SQ FT | $0.0100 | $0.0600 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 7 | Z0004562 | COMB C C&G REM & REPL | 884 | FOOT | $36.00 | $34.00 | $37.65 | $36.00 | $35.70 | $40.18 | |
| 8 | Z0018500 | DRAINAGE STR CLEANED | 62 | EACH | $325.00 | $325.00 | $350.00 | $350.00 | $325.00 | $350.00 | |
| 9 | Z0018600 | DRAINAGE STR RECONST | 2 | EACH | $1,250.00 | $1,250.00 | $2,000.00 | $2,000.00 | $1,250.00 | $1,250.00 | |
| 10 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $12.00 | $20.00 | $12.00 | $20.00 | $21.25 | $16.00 | |
| 11 | Z0033700 | LONG JOINT SEALANT | 21,120 | FOOT | $1.00 | $1.50 | $2.35 | $2.35 | $1.98 | $2.21 | |
| 12 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 13 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 14 | 20100210 | TREE REMOV OVER 15 | 26 | UNIT | $100.00 | $90.00 | $90.00 | $30.00 | $49.00 | $90.00 | |
| 15 | 20101300 | TREE PRUN 1-10 | 3 | EACH | $40.00 | $40.00 | $40.00 | $50.00 | $250.00 | $40.00 | |
| 16 | 20101350 | TREE PRUN OVER 10 | 19 | EACH | $150.00 | $150.00 | $150.00 | $85.00 | $100.00 | $150.00 | |
| 17 | 20200100 | EARTH EXCAVATION | 21 | CU YD | $55.00 | $60.00 | $63.00 | $65.00 | $63.00 | $54.30 | |
| 18 | 21101615 | TOPSOIL F & P 4 | 380 | SQ YD | $7.00 | $7.00 | $5.00 | $7.00 | $5.00 | $8.00 | |
| 19 | 25200110 | SODDING SALT TOLERANT | 380 | SQ YD | $10.00 | $10.00 | $15.98 | $10.00 | $15.98 | $8.00 | |
| 20 | 35501308 | HMA BASE CSE 6 | 67 | SQ YD | $70.00 | $85.00 | $65.00 | $58.00 | $95.00 | $65.00 | |
| 21 | 40600290 | BIT MATLS TACK CT | 15,263 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 22 | 40600400 | MIX CR JTS FLANGEWYS | 54 | TON | $75.00 | $50.00 | $435.00 | $315.00 | $290.00 | $325.00 | |
| 23 | 40600982 | HMA SURF REM BUTT JT | 746 | SQ YD | $1.00 | $0.0100 | $1.00 | $16.00 | $1.00 | $13.00 | |
| 24 | 40604060 | HMA SC IL-9.5 D N50 | 8 | TON | $285.00 | $150.00 | $150.00 | $180.00 | $275.00 | $155.00 | |
| 25 | 40604062 | HMA SC IL-9.5 D N70 | 2,849 | TON | $74.25 | $82.50 | $67.50 | $77.75 | $65.00 | $75.25 | |
| 26 | 42001300 | PROTECTIVE COAT | 412 | SQ YD | $1.00 | $1.00 | $1.05 | $1.00 | $1.05 | $1.09 | |
| 27 | 42300200 | PCC DRIVEWAY PAVT 6 | 27 | SQ YD | $86.00 | $75.00 | $78.75 | $75.00 | $78.75 | $72.77 | |
| 28 | 42400200 | PC CONC SIDEWALK 5 | 2,119 | SQ FT | $7.25 | $7.00 | $7.35 | $7.00 | $7.35 | $8.63 | |
| 29 | 42400800 | DETECTABLE WARNINGS | 126 | SQ FT | $30.00 | $33.00 | $34.65 | $33.00 | $34.65 | $27.15 | |
| 30 | 44000155 | HMA SURF REM 1 1/2 | 33,917 | SQ YD | $2.20 | $2.75 | $1.90 | $2.20 | $2.50 | $2.65 | |
| 31 | 44000200 | DRIVE PAVEMENT REM | 93 | SQ YD | $23.00 | $22.00 | $23.10 | $22.00 | $30.00 | $12.30 | |
| 32 | 44000600 | SIDEWALK REM | 1,969 | SQ FT | $1.80 | $2.00 | $2.10 | $2.00 | $2.10 | $1.57 | |
| 33 | 44201803 | CL D PATCH T2 13 | 350 | SQ YD | $31.00 | $30.00 | $130.00 | $90.00 | $110.00 | $104.06 | |
| 34 | 44201807 | CL D PATCH T3 13 | 100 | SQ YD | $31.00 | $30.00 | $128.00 | $90.00 | $110.00 | $104.08 | |
| 35 | 44201809 | CL D PATCH T4 13 | 200 | SQ YD | $31.00 | $30.00 | $120.00 | $80.00 | $110.00 | $104.06 | |
| 36 | 60300105 | FR & GRATES ADJUST | 10 | EACH | $400.00 | $400.00 | $400.00 | $460.00 | $400.00 | $400.00 | |
| 37 | 60300305 | FR & LIDS ADJUST | 10 | EACH | $450.00 | $450.00 | $400.00 | $460.00 | $450.00 | $450.00 | |
| 38 | 66900200 | NON SPL WASTE DISPOSL | 21 | CU YD | $110.00 | $100.00 | $125.00 | $80.00 | $125.00 | $82.50 | |
| 39 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,900.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | |
| 40 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,950.00 | $3,800.00 | $3,800.00 | $3,800.00 | $3,800.00 | $2,750.00 | |
| 41 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $900.00 | $500.00 | $500.00 | $500.00 | $500.00 | $1,500.00 | |
| 42 | 66901006 | REG SUB MON | 3 | CAL DA | $680.00 | $675.00 | $675.00 | $675.00 | $675.00 | $760.00 | |
| 43 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,000.00 | $3,300.00 | $2,100.00 | $3,000.00 | $2,250.00 | $3,600.00 | |
| 44 | 67100100 | MOBILIZATION | 1 | L SUM | $43,100.00 | $45,000.00 | $72,036.74 | $45,500.00 | $42,939.94 | $51,000.00 | |
| 45 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $66,700.00 | $38,500.00 | $9,300.00 | $7,700.00 | $82,600.00 | $1.00 | |
| 46 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $100.00 | $1.00 | $1.00 | $1.00 | |
| 47 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $2,600.00 | $100.00 | $5,000.00 | $1,950.00 | $20,000.00 | |
| 48 | 70300100 | SHORT TERM PAVT MKING | 27,729 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.7500 | |
| 49 | 70300150 | SHRT TRM PAVT MK REM | 9,243 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 50 | 70300210 | TEMP PVT MK LTR & SYM | 255 | SQ FT | $0.0100 | $1.20 | $0.0100 | $1.00 | $0.0100 | $1.50 | |
| 51 | 70300220 | TEMP PVT MK LINE 4 | 23,759 | FOOT | $0.0100 | $0.2400 | $0.0100 | $0.2400 | $0.0100 | $0.4500 | |
| 52 | 70300240 | TEMP PVT MK LINE 6 | 948 | FOOT | $0.0100 | $0.4200 | $0.0100 | $0.2800 | $0.0100 | $0.6500 | |
| 53 | 70300250 | TEMP PVT MK LINE 8 | 200 | FOOT | $0.0100 | $1.00 | $0.0100 | $0.5000 | $0.0100 | $0.9000 | |
| 54 | 70300260 | TEMP PVT MK LINE 12 | 935 | FOOT | $0.0100 | $0.8500 | $0.0100 | $0.7500 | $0.0100 | $1.75 | |
| 55 | 70300280 | TEMP PVT MK LINE 24 | 243 | FOOT | $0.0100 | $1.85 | $0.0100 | $2.00 | $0.0100 | $2.50 | |
| 56 | 70300520 | PAVT MARK TAPE T3 4 | 13,864 | FOOT | $0.0100 | $0.9500 | $0.4000 | $0.7500 | $0.7500 | $0.9500 | |
| 57 | 78000100 | THPL PVT MK LTR & SYM | 255 | SQ FT | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | |
| 58 | 78000200 | THPL PVT MK LINE 4 | 23,759 | FOOT | $0.5500 | $0.5500 | $0.6300 | $0.5500 | $0.6300 | $0.5500 | |
| 59 | 78000400 | THPL PVT MK LINE 6 | 948 | FOOT | $0.7500 | $0.7500 | $0.9500 | $0.7500 | $0.9500 | $0.7500 | |
| 60 | 78000500 | THPL PVT MK LINE 8 | 200 | FOOT | $1.00 | $1.00 | $1.25 | $1.00 | $1.25 | $1.00 | |
| 61 | 78000600 | THPL PVT MK LINE 12 | 935 | FOOT | $1.50 | $1.50 | $2.00 | $1.50 | $2.00 | $1.50 | |
| 62 | 78000650 | THPL PVT MK LINE 24 | 243 | FOOT | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | |
| 63 | 78100100 | RAISED REFL PAVT MKR | 597 | EACH | $22.50 | $22.50 | $24.00 | $22.50 | $24.00 | $22.50 | |
| 64 | 78300200 | RAISED REF PVT MK REM | 597 | EACH | $7.00 | $13.00 | $14.50 | $19.00 | $3.00 | $9.00 | |
| 65 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $1,000.00 | $810.00 | $2,200.00 | $2,200.00 | $807.70 | $2,308.42 | |
| 66 | 88600600 | DET LOOP REPL | 778 | FOOT | $15.90 | $16.00 | $17.00 | $17.00 | $15.90 | $17.84 | |
| 67 | 89500400 | RELOC EX PED PUSH-BUT | 6 | EACH | $360.00 | $360.00 | $450.00 | $450.00 | $358.20 | $472.18 | |
| 68 | 89502376 | REBUILD EX HANDHOLE | 2 | EACH | $1,400.00 | $1,400.00 | $2,500.00 | $2,300.00 | $1,398.30 | $2,413.35 |