2020-040-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K-Five Construction Corporation Low bidder | $1,443,742 | ||
| 2 | Gallagher Asphalt Corporation | $1,480,278 | +2.5% | |
| 3 | Bigane Paving Company | $1,689,756 | +17.0% | |
| 4 | MAT Construction Leasing, Inc. | $1,711,277 | +18.5% | |
| 5 | D. Construction, Inc. | $2,431,210 | +68.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K-Five Construc… | #2 Gallagher Aspha… | #3 Bigane Paving C… | #4 MAT Constructio… | #5 D. Construction… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $500.00 | $1,400.00 | $8,000.00 | $4,500.00 | $2,000.00 | |
| 2 | X4060995 | TEMPORARY RAMP SPL | 60 | SQ YD | $25.00 | $20.00 | $50.00 | $15.00 | $35.00 | |
| 3 | X4240800 | DETECTABLE WARN SPL | 30 | SQ FT | $40.00 | $46.00 | $32.00 | $40.00 | $45.00 | |
| 4 | X4400501 | COMB C&G REMOV REPL < = 10FT | 100 | FOOT | $45.00 | $52.00 | $38.00 | $45.00 | $50.00 | |
| 5 | X5537800 | SS CLEANED 12 | 1,000 | FOOT | $3.00 | $3.00 | $3.00 | $2.50 | $2.75 | |
| 6 | X6030310 | FR & LIDS ADJUST SPL | 96 | EACH | $650.00 | $710.00 | $750.00 | $650.00 | $715.00 | |
| 7 | X7030005 | TEMP PAVT MKING REMOV | 6,822 | SQ FT | $0.0100 | $0.0100 | $0.5000 | $0.0100 | $0.0100 | |
| 8 | Z0004562 | COMB C C&G REM & REPL | 1,399 | FOOT | $35.00 | $40.00 | $38.00 | $35.00 | $605.00 | |
| 9 | Z0018500 | DRAINAGE STR CLEANED | 83 | EACH | $300.00 | $300.00 | $300.00 | $550.00 | $39.50 | |
| 10 | Z0030850 | TEMP INFO SIGNING | 89 | SQ FT | $11.75 | $18.00 | $17.00 | $15.00 | $25.00 | |
| 11 | Z0033700 | LONG JOINT SEALANT | 21,288 | FOOT | $0.0100 | $2.30 | $2.20 | $2.01 | $2.31 | |
| 12 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 13 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 14 | 20200100 | EARTH EXCAVATION | 5 | CU YD | $70.00 | $80.00 | $50.00 | $70.00 | $77.00 | |
| 15 | 21101615 | TOPSOIL F & P 4 | 229 | SQ YD | $8.00 | $5.00 | $9.00 | $8.00 | $5.50 | |
| 16 | 25200110 | SODDING SALT TOLERANT | 229 | SQ YD | $10.00 | $23.00 | $16.00 | $14.00 | $25.30 | |
| 17 | 25200200 | SUPPLE WATERING | 0.1 | UNIT | $0.1000 | $250.00 | $150.00 | $20.00 | $275.00 | |
| 18 | 40600290 | BIT MATLS TACK CT | 26,315 | POUND | $0.0100 | $0.0100 | $1.00 | $0.8000 | $0.0100 | |
| 19 | 40600400 | MIX CR JTS FLANGEWYS | 117 | TON | $50.00 | $50.00 | $150.00 | $150.00 | $150.00 | |
| 20 | 40600982 | HMA SURF REM BUTT JT | 128 | SQ YD | $0.0100 | $18.00 | $40.00 | $4.20 | $0.0100 | |
| 21 | 40602985 | HMA BC IL-9.5 N70 | 4,367 | TON | $92.00 | $77.00 | $85.00 | $83.00 | $67.00 | |
| 22 | 40604172 | P HMA SC IL-9.5 E N70 | 3,821 | TON | $107.00 | $94.00 | $101.00 | $105.00 | $83.00 | |
| 23 | 42001300 | PROTECTIVE COAT | 359 | SQ YD | $2.00 | $2.30 | $1.00 | $2.00 | $2.20 | |
| 24 | 42400200 | PC CONC SIDEWALK 5 | 155 | SQ FT | $14.00 | $16.00 | $8.00 | $14.00 | $15.90 | |
| 25 | 42400410 | PC CONC SIDEWALK 8 | 200 | SQ FT | $16.00 | $18.25 | $10.00 | $16.00 | $20.30 | |
| 26 | 44000164 | HMA SURF REM 3 3/4 | 38,985 | SQ YD | $4.00 | $2.70 | $4.50 | $4.20 | $2.90 | |
| 27 | 44000600 | SIDEWALK REM | 355 | SQ FT | $3.00 | $3.45 | $2.00 | $3.00 | $3.30 | |
| 28 | 44201803 | CL D PATCH T2 13 | 1,120 | SQ YD | $35.00 | $90.00 | $80.00 | $111.00 | $120.00 | |
| 29 | 44201807 | CL D PATCH T3 13 | 680 | SQ YD | $35.00 | $82.00 | $75.00 | $110.00 | $120.00 | |
| 30 | 44201809 | CL D PATCH T4 13 | 1,660 | SQ YD | $35.00 | $76.00 | $75.00 | $109.00 | $120.00 | |
| 31 | 60252800 | CB RECONST | 4 | EACH | $2,000.00 | $2,180.00 | $1,100.00 | $2,000.00 | $2,200.00 | |
| 32 | 66900200 | NON SPL WASTE DISPOSL | 5 | CU YD | $125.00 | $102.00 | $140.00 | $125.00 | $500.00 | |
| 33 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,400.00 | $1,400.00 | $1,500.00 | $1,400.00 | $1,650.00 | |
| 34 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,100.00 | $2,100.00 | $2,100.00 | $3,800.00 | $2,200.00 | |
| 35 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,900.00 | $1,900.00 | $1,900.00 | $500.00 | $2,200.00 | |
| 36 | 66901006 | REG SUB MON | 1 | CAL DA | $1,000.00 | $1,000.00 | $1,000.00 | $575.00 | $1,045.00 | |
| 37 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,300.00 | $500.00 | $3,000.00 | $2,500.00 | $4,000.00 | |
| 38 | 67100100 | MOBILIZATION | 1 | L SUM | $86,000.00 | $88,962.96 | $98,000.00 | $40,000.00 | $80,000.00 | |
| 39 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $10,500.00 | $6,200.00 | $8,000.00 | $1.00 | $96,270.00 | |
| 40 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $100.00 | $1.00 | $0.0100 | |
| 41 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $900.00 | $1,000.00 | $100.00 | $9,400.00 | $0.0100 | |
| 42 | 70300100 | SHORT TERM PAVT MKING | 10,804 | FOOT | $0.0100 | $0.0100 | $1.00 | $0.8500 | $0.0100 | |
| 43 | 70300150 | SHRT TRM PAVT MK REM | 3,602 | SQ FT | $0.0100 | $0.0100 | $2.00 | $1.00 | $0.0100 | |
| 44 | 70300220 | TEMP PVT MK LINE 4 | 17,077 | FOOT | $0.0100 | $0.0100 | $0.5000 | $0.2500 | $0.0100 | |
| 45 | 70300240 | TEMP PVT MK LINE 6 | 182 | FOOT | $0.0100 | $0.0100 | $1.00 | $0.0500 | $0.0100 | |
| 46 | 70300280 | TEMP PVT MK LINE 24 | 69 | FOOT | $0.0100 | $0.0100 | $3.00 | $1.00 | $0.0100 | |
| 47 | 70300520 | PAVT MARK TAPE T3 4 | 2,701 | FOOT | $1.25 | $4.50 | $1.60 | $0.9500 | $0.0100 | |
| 48 | 78000200 | THPL PVT MK LINE 4 | 17,077 | FOOT | $0.6500 | $0.7500 | $0.8000 | $0.6500 | $0.8300 | |
| 49 | 78000400 | THPL PVT MK LINE 6 | 182 | FOOT | $1.02 | $3.50 | $2.00 | $1.02 | $3.85 | |
| 50 | 78000650 | THPL PVT MK LINE 24 | 69 | FOOT | $4.05 | $9.00 | $5.00 | $4.05 | $9.90 | |
| 51 | 78300200 | RAISED REF PVT MK REM | 958 | EACH | $12.50 | $6.75 | $2.00 | $1.00 | $7.00 | |
| 52 | 88600600 | DET LOOP REPL | 50 | FOOT | $30.00 | $30.00 | $30.00 | $30.00 | $33.00 |