2020-021-PP
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K-Five Construction Corporation Low bidder | $2,539,731 | ||
| 2 | D. Construction, Inc. | $4,470,031 | +76.0% | |
| 3 | Gallagher Asphalt Corporation | $4,777,527 | +88.1% | |
| 4 | R. W. Dunteman Company | $7,427,995 | +192.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K-Five Construc… | #2 D. Construction… | #3 Gallagher Aspha… | #4 R. W. Dunteman … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X4405020 | LONG PAR DEP REM 2 | 86,250 | FOOT | $6.19 | $10.00 | $8.25 | $12.17 | |
| 2 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $45,000.00 | $293,000.00 | $499,000.00 | $846,928.14 | |
| 3 | X7030005 | TEMP PAVT MKING REMOV | 20,935 | SQ FT | $0.0100 | $2.00 | $0.0100 | $0.3000 | |
| 4 | X8730312 | EC C LEAD 18 4C TW SH | 50 | FOOT | $8.00 | $15.95 | $9.50 | $8.00 | |
| 5 | X8850102 | INDUCTION LOOP | 122 | FOOT | $110.00 | $94.60 | $140.00 | $110.00 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 7 | 40600290 | BIT MATLS TACK CT | 14,769 | POUND | $0.0100 | $0.0100 | $5.00 | $0.3100 | |
| 8 | 40600400 | MIX CR JTS FLANGEWYS | 50 | TON | $350.00 | $50.00 | $700.00 | $70.00 | |
| 9 | 40604172 | P HMA SC IL-9.5 E N70 | 3,676 | TON | $85.00 | $225.00 | $220.00 | $442.47 | |
| 10 | 44000157 | HMA SURF REM 2 | 32,820 | SQ YD | $4.00 | $15.00 | $17.00 | $35.19 | |
| 11 | 44201803 | CL D PATCH T2 13 | 993 | SQ YD | $251.13 | $200.00 | $275.00 | $318.64 | |
| 12 | 44201807 | CL D PATCH T3 13 | 459 | SQ YD | $251.13 | $175.00 | $250.00 | $358.29 | |
| 13 | 44201809 | CL D PATCH T4 13 | 60 | SQ YD | $251.13 | $175.00 | $225.00 | $344.50 | |
| 14 | 44209000 | LONG PART DEPTH PATCH | 3,227 | TON | $221.65 | $225.00 | $280.00 | $425.53 | |
| 15 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,500.00 | $4,500.00 | $3,000.00 | $4,000.00 | |
| 16 | 67100100 | MOBILIZATION | 1 | L SUM | $155,000.00 | $174,000.00 | $377,000.00 | $618,348.01 | |
| 17 | 70107025 | CHANGEABLE MESSAGE SN | 160 | CAL DA | $30.00 | $50.00 | $35.00 | $35.00 | |
| 18 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $25,000.00 | $10,000.00 | $45,000.00 | $20,000.00 | |
| 19 | 70300520 | PAVT MARK TAPE T3 4 | 8,746 | FOOT | $0.5000 | $0.0100 | $5.00 | $1.10 | |
| 20 | 78000200 | THPL PVT MK LINE 4 | 33,830 | FOOT | $0.6500 | $6.34 | $1.00 | $0.6500 | |
| 21 | 78000500 | THPL PVT MK LINE 8 | 1,800 | FOOT | $2.00 | $12.66 | $3.00 | $2.00 | |
| 22 | 78004355 | PREF PL PM TD INL L5 | 13,300 | FOOT | $5.75 | $14.53 | $10.00 | $5.75 | |
| 23 | 78100100 | RAISED REFL PAVT MKR | 1,330 | EACH | $31.25 | $189.75 | $50.00 | $31.25 | |
| 24 | 78300200 | RAISED REF PVT MK REM | 1,330 | EACH | $21.92 | $10.00 | $25.00 | $13.80 |