2019-170-I
- Let date
- Friday, January 15, 2021
- Contract
- 62K43 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- The improvement consists of Litter/Debris Removal from the edge of the pavement to the pedestrian barrier on 1) FAI 94: I-94 from I-90/94 (Dan Ryan Expwy) to I-80; 2) FAP 341: Stony Island from I-94 to US 12(95th St); 3) FAU 1574: 103rd St from Cottage Groove to Stony Island.
- Classification
- Litter/Debris Removal from the edge of the pavement to the pedestrian barrier on 1) FAI 94: I-94 from I-90/94
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | 10x Contractors LLC Low bidder | $214,500 | ||
| 2 | Vixen Construction, Inc. | $759,000 | +253.8% | |
| 3 | Lion Construction 1, LLC | $1,493,250 | +596.2% |