2019-168-I
- Let date
- Friday, January 15, 2021
- Contract
- 62K41 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- The improvement consists of Litter/Debris Removal from the edge of the pavement to the pedestrian barrier on I-90/94 (Dan Ryan Expy) from Congress Pkwy to I-57/I-94 Bishop Ford Expy).
- Classification
- Litter/Debris Removal from the edge of the pavement to the pedestrian barrier on I-90/94 (Dan Ryan Expy) from
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | 10x Contractors LLC Low bidder | $280,800 | ||
| 2 | Vixen Construction, Inc. | $993,600 | +253.8% | |
| 3 | Lion Construction 1, LLC | $1,663,200 | +492.3% |