2019-128-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kiewit Infrastructure Co. Low bidder | $654,013 | ||
| 2 | GRANITE CONSTRUCTION COMPANY | $767,935 | +17.4% | |
| 3 | Rausch Infrastructure, LLC | $841,790 | +28.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kiewit Infrastr… | #2 GRANITE CONSTRU… | #3 Rausch Infrastr… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $280,000.00 | $100,000.00 | $235,000.00 | |
| 2 | Z0001905 | STRUCT STEEL REPAIR | 3,450 | POUND | $72.00 | $164.00 | $130.00 | |
| 3 | Z0012754 | STR REP CON DP = < 5 | 49 | SQ FT | $390.00 | $350.00 | $490.00 | |
| 4 | Z0012755 | STR REP CON DP OVER 5 | 87 | SQ FT | $435.00 | $350.00 | $575.00 | |
| 5 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $25,000.00 | $5,000.00 | $35,000.00 | |
| 6 | 59000200 | EPOXY CRACK INJECTION | 19 | FOOT | $212.00 | $200.00 | $130.00 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $39,000.00 | $45,000.00 | $45,000.00 | |
| 8 | 70107025 | CHANGEABLE MESSAGE SN | 21 | CAL DA | $30.00 | $35.00 | $85.00 |