2019-032-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | R. W. Dunteman Company Low bidder | $1,600,201 | ||
| 2 | K-Five Construction Corporation | $2,550,000 | +59.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 R. W. Dunteman … | #2 K-Five Construc… |
|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 171 | SQ FT | $1.25 | $8.00 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 462.6 | SQ FT | $15.00 | $15.00 | |
| 3 | 40600290 | BIT MATLS TACK CT | 13,651 | POUND | $1.03 | $0.0100 | |
| 4 | 40600400 | MIX CR JTS FLANGEWYS | 30 | TON | $85.00 | $2,000.00 | |
| 5 | 40600982 | HMA SURF REM BUTT JT | 590 | SQ YD | $1.78 | $0.0100 | |
| 6 | 40603340 | HMA SC "D" N70 | 2,199 | TON | $328.09 | $450.00 | |
| 7 | 44000157 | HMA SURF REM 2 | 19,633 | SQ YD | $32.90 | $60.00 | |
| 8 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,000.00 | $3,745.86 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $96,073.40 | $181,375.32 | |
| 10 | 70300520 | PAVT MARK TAPE T3 4 | 513 | FOOT | $0.9000 | $1.70 | |
| 11 | 78000100 | THPL PVT MK LTR & SYM | 40 | SQ FT | $15.00 | $17.00 | |
| 12 | 78000200 | THPL PVT MK LINE 4 | 5,606 | FOOT | $4.73 | $5.00 | |
| 13 | 78000650 | THPL PVT MK LINE 24 | 36 | FOOT | $29.00 | $33.00 | |
| 14 | 78100100 | RAISED REFL PAVT MKR | 670 | EACH | $61.59 | $65.00 | |
| 15 | 78300200 | RAISED REF PVT MK REM | 670 | EACH | $23.33 | $30.00 | |
| 16 | 88600600 | DET LOOP REPL | 450 | FOOT | $32.00 | $35.00 |