2019-029-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | J. A. Johnson Paving Company Low bidder | $4,887,777 | ||
| 2 | R. W. Dunteman Company | $8,737,802 | +78.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J. A. Johnson P… | #2 R. W. Dunteman … |
|---|---|---|---|---|---|---|---|
| 1 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $25,000.00 | $309,000.00 | |
| 2 | X7030005 | TEMP PAVT MKING REMOV | 1,743 | SQ FT | $0.0100 | $0.8500 | |
| 3 | Z0030850 | TEMP INFO SIGNING | 925.2 | SQ FT | $25.00 | $15.00 | |
| 4 | 40600290 | BIT MATLS TACK CT | 76,209 | POUND | $0.0100 | $0.3500 | |
| 5 | 40600400 | MIX CR JTS FLANGEWYS | 165 | TON | $200.00 | $136.56 | |
| 6 | 40600982 | HMA SURF REM BUTT JT | 3,310 | SQ YD | $1.00 | $3.00 | |
| 7 | 40603340 | HMA SC "D" N70 | 12,275 | TON | $205.00 | $392.02 | |
| 8 | 44000157 | HMA SURF REM 2 | 109,592 | SQ YD | $15.25 | $24.45 | |
| 9 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,500.00 | $3,300.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $287,230.72 | $522,000.00 | |
| 11 | 70300520 | PAVT MARK TAPE T3 4 | 5,230 | FOOT | $0.0100 | $1.05 | |
| 12 | 78000100 | THPL PVT MK LTR & SYM | 800 | SQ FT | $3.75 | $3.75 | |
| 13 | 78000200 | THPL PVT MK LINE 4 | 52,098 | FOOT | $1.11 | $1.11 | |
| 14 | 78000400 | THPL PVT MK LINE 6 | 4,932 | FOOT | $1.76 | $1.76 | |
| 15 | 78000500 | THPL PVT MK LINE 8 | 396 | FOOT | $2.35 | $2.35 | |
| 16 | 78000600 | THPL PVT MK LINE 12 | 667 | FOOT | $3.52 | $3.52 | |
| 17 | 78000650 | THPL PVT MK LINE 24 | 1,657 | FOOT | $7.04 | $7.04 | |
| 18 | 78100100 | RAISED REFL PAVT MKR | 2,824 | EACH | $37.11 | $37.11 | |
| 19 | 78300200 | RAISED REF PVT MK REM | 2,824 | EACH | $1.00 | $2.00 | |
| 20 | 88600600 | DET LOOP REPL | 6,697 | FOOT | $18.00 | $18.00 |