2019-023-DM
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Scanlon Excavating & Concrete, Inc. Low bidder | $83,910 | ||
| 2 | Galaxy Environmental Inc. | $104,681 | +24.8% | |
| 3 | Schwartz Excavating, Inc. | $114,628 | +36.6% | |
| 4 | Lion Construction 1, LLC | $247,249 | +194.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Scanlon Excavat… | #2 Galaxy Environm… | #3 Schwartz Excava… | #4 Lion Constructi… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X5420615 | PIPE CULV CLEANED 15 | 50 | FOOT | $20.00 | $9.71 | $103.51 | $50.00 | |
| 2 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $25,000.00 | $39,000.00 | $21,600.00 | $100,000.00 | |
| 3 | Z0007602 | BLDG REMOV NO 2 | 1 | L SUM | $3,500.00 | $5,000.00 | $3,348.00 | $50,000.00 | |
| 4 | Z0015500 | DEBRIS REMOVAL | 1 | L SUM | $2,500.00 | $7,500.00 | $4,461.50 | $10,000.00 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $20.00 | $24.00 | $19.46 | $50.00 | |
| 6 | Z0049901 | R&D NON-FR ASB BLD 1 | 1 | L SUM | $28,000.00 | $7,000.00 | $36,720.00 | $10,000.00 | |
| 7 | Z0049902 | R&D NON-FR ASB BLD 2 | 1 | L SUM | $1,000.00 | $2,000.00 | $0.00 | $500.00 | |
| 8 | Z0055905 | TEMP CONSTR FENCE | 430 | FOOT | $6.00 | $3.00 | $7.05 | $40.00 | |
| 9 | 21101625 | TOPSOIL F & P 6 | 672 | SQ YD | $10.00 | $19.00 | $10.80 | $15.00 | |
| 10 | 25000200 | SEEDING CL 2 | 0.14 | ACRE | $2,500.00 | $16,000.00 | $16,200.00 | $20,000.00 | |
| 11 | 25000400 | NITROGEN FERT NUTR | 12 | POUND | $5.00 | $4.00 | $5.40 | $10.00 | |
| 12 | 25000500 | PHOSPHORUS FERT NUTR | 12 | POUND | $5.00 | $4.00 | $5.40 | $10.00 | |
| 13 | 25000600 | POTASSIUM FERT NUTR | 12 | POUND | $5.00 | $4.00 | $5.40 | $10.00 | |
| 14 | 25100105 | MULCH METHOD 1 | 0.14 | ACRE | $15,000.00 | $12,000.00 | $21,600.00 | $40,000.00 | |
| 15 | 28000400 | PERIMETER EROS BAR | 430 | FOOT | $4.00 | $8.00 | $3.78 | $20.00 | |
| 16 | 44000200 | DRIVE PAVEMENT REM | 372 | SQ YD | $6.00 | $25.00 | $10.09 | $27.00 | |
| 17 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $500.00 | $1,000.00 | $3,456.00 | $1,000.00 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $4,500.00 | $8,600.00 | $10,800.00 | $13,995.00 |