1515-B-R-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sumit Construction Co., Inc. Low bidder | $160,881 | ||
| 2 | D. Construction, Inc. | $263,886 | +64.0% | |
| 3 | Lakes & Rivers Contracting, Inc. | $264,375 | +64.3% | |
| 4 | Kovilic Construction Company, Inc. | $380,570 | +136.6% | |
| 5 | Rausch Infrastructure LLC | $413,148 | +156.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sumit Construct… | #2 D. Construction… | #3 Lakes & Rivers … | #4 Kovilic Constru… | #5 Rausch Infrastr… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0001905 | STRUCT STEEL REPAIR | 4,740 | POUND | $20.00 | $40.00 | $39.75 | $45.00 | $57.00 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $18.00 | $27.50 | $15.00 | $50.00 | $20.00 | |
| 3 | 50300225 | CONC STRUCT | 5 | CU YD | $4,500.00 | $6,000.00 | $10,000.00 | $20,000.00 | $5,500.00 | |
| 4 | 50800205 | REINF BARS, EPOXY CTD | 870 | POUND | $6.50 | $3.50 | $3.00 | $10.00 | $12.00 | |
| 5 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,000.00 | $4,000.00 | $3,000.00 | $1,000.00 | $5,000.00 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $15,000.00 | $15,825.00 | $4,279.00 | $20,000.00 | $24,000.00 | |
| 7 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $10,000.00 | $1.00 | $200.00 | $25,000.00 | $40,000.00 | |
| 8 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $100.00 | $5,000.00 | $10,000.00 |