1515.2B-BR
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $103,640 | ||
| 2 | Sumit Construction Co., Inc. | $122,772 | +18.5% | |
| 3 | Path Construction Company, Inc. | $142,500 | +37.5% | |
| 4 | Rausch Infrastructure LLC | $174,608 | +68.5% | |
| 5 | Areatha Construction Co., Inc. | $189,964 | +83.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Sumit Construct… | #3 Path Constructi… | #4 Rausch Infrastr… | #5 Areatha Constru… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0900046 | PREF JNT SEAL 1" | 85 | FOOT | $80.00 | $95.00 | $75.00 | $155.00 | $250.00 | |
| 2 | X0900058 | PREF JOINT SEAL 2" | 93.2 | FOOT | $100.00 | $100.00 | $80.00 | $195.00 | $250.00 | |
| 3 | X5870015 | BR DK CONCRETE SEALER | 5,570 | SQ FT | $1.00 | $1.00 | $1.00 | $2.00 | $3.00 | |
| 4 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $15,000.00 | $35,000.00 | $40,000.00 | $35,000.00 | $60,000.00 | |
| 5 | Z0001800 | APPROACH SL REP (PD) | 0.33 | SQ YD | $6,500.00 | $3,300.00 | $7,500.00 | $8,000.00 | $5,000.00 | |
| 6 | Z0010400 | CLEANING BRIDGE SEATS | 304 | SQ FT | $10.00 | $12.00 | $6.00 | $16.00 | $3.40 | |
| 7 | Z0012754 | STR REP CON DP = < 5 | 210 | SQ FT | $165.00 | $165.00 | $170.00 | $230.00 | $125.00 | |
| 8 | Z0041895 | POLYMER CONCRETE | 10.35 | CU FT | $900.00 | $1,200.00 | $2,400.00 | $900.00 | $2,200.00 | |
| 9 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $4,000.00 | $1,000.00 | $2,800.00 | $7,500.00 | $2,000.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $5,800.00 | $10,000.00 | $9,860.00 | $9,500.00 | $11,000.00 |