1BidsJun 12, 2026 to Jun 12, 2026
0Wins (low bidder)
0.0%Win rate
$0Total won
Competitor scorecard
Last 5 years in Illinois0.0%Win rate0 of 1 bids
—Average bid vs estimate
—Winning bids vs estimate
+47.2%Over the low bid when they loseAverage field: 4.0 bidders
| Head to head | Times met | Beat them | Lost to them | Record |
|---|---|---|---|---|
| Foundation Mechanics | 1 | 0 | 1 | 0% |
| Sangamo Construction Company | 1 | 1 | 0 | 100% |
| MYS, Incorporated | 1 | 0 | 1 | 0% |
| Let date | Contract | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Jun 12, 2026 | 70H72 | MBPM 2026-1Vermilion · District 5 | 3 of 4 | $394,253 | $267,850MYS, Incorporated | +47.2% |
Subcontracts on active jobs 0
No subcontracts on TxDOT's active contract list.