$32.90Avg low bid / EACH
$26.59Avg of all bids
—Avg engineer's estimate
16Jobs · 7,590 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 5 | 370 | $27.15 | $20.74 |
| 2022 | 5 | 2,444 | $18.78 | $20.99 |
| 2021 | 2 | 4,202 | $40.05 | $30.49 |
| 2020 | 3 | 563 | $44.97 | $34.98 |
| 2018 | 1 | 11 | $15.05 | $20.90 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 22, 2023 | 62U36 | CookDistrict 1 | 92 EACH | $26.75 | Capital Industrial Services, LLC |
| Sep 22, 2023 | 76M43 | JerseyDistrict 8 | 36 EACH | $16.50 | Stutz Excavating, Inc. |
| Aug 4, 2023 | 60R77 | CookDistrict 1 | 100 EACH | $25.00 | Lorig Construction Company |
| Aug 4, 2023 | 62P00 | CookDistrict 1 | 112 EACH | $35.00 | Lorig Construction Company |
| Apr 28, 2023 | 62U00 | CookDistrict 1 | 30 EACH | $19.00 | Rausch Infrastructure, LLC |
| Jun 17, 2022 | 61H44 | CookDistrict 1 | 22 EACH | $50.00 | Alliance Contractors, Inc. |
| Apr 29, 2022 | 62M58 | LakeDistrict 1 | 108 EACH | $30.00 | Lorig Construction Company |
| Apr 29, 2022 | 62P45 | CookDistrict 1 | 2,260 EACH | $17.00 | Judlau Contracting, Inc. |
| Mar 11, 2022 | 62M55 | WillDistrict 1 | 26 EACH | $13.20 | D. Construction, Inc. |
| Mar 11, 2022 | 62M64 | DupageDistrict 1 | 28 EACH | $100.00 | Lorig Construction Company |
| Jun 11, 2021 | 70B99 | ChampaignDistrict 5 | 4,129 EACH | $40.49 | William Charles Construction Company, LLC and White Construction, LLC JV |
| Mar 5, 2021 | 62M29 | CookDistrict 1 | 73 EACH | $15.40 | D. Construction, Inc. |
| Nov 6, 2020 | 76N19 | MadisonDistrict 8 | 12 EACH | $12.24 | Keller Construction, Inc. |
| Nov 6, 2020 | 62M63 | WillDistrict 1 | 326 EACH | $52.53 | D. Construction, Inc. |
| Jan 17, 2020 | 66H21 | LasalleDistrict 3 | 225 EACH | $35.75 | D. Construction, Inc. |
| Apr 27, 2018 | 87664 | DekalbDistrict 3 | 11 EACH | $15.05 | Curran Contracting Company |