$738.12Avg low bid / EACH
$603.74Avg of all bids
—Avg engineer's estimate
5Jobs · 49 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2020 | 1 | 16 | $925.00 | $542.96 |
| 2019 | 4 | 33 | $647.52 | $654.34 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2020 | 61G35 | CookDistrict 1 | 16 EACH | $925.00 | A Lamp Concrete Contractors, Inc. |
| Sep 20, 2019 | 61F58 | MchenryDistrict 1 | 4 EACH | $793.00 | Copenhaver Construction, Inc. |
| Jun 14, 2019 | 61F37 | CookDistrict 1 | 2 EACH | $503.00 | Alliance Contractors, Inc. |
| Apr 26, 2019 | 61F39 | CookDistrict 1 | 12 EACH | $620.00 | J. Nardulli Concrete, Inc. |
| Apr 26, 2019 | 61F64 | WillDistrict 1 | 15 EACH | $650.00 | K-Five Construction Corporation |