$58.38Avg low bid / CU YD
$61.67Avg of all bids
—Avg engineer's estimate
5Jobs · 5,826 CU YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 1 | 2,265 | $48.00 | $63.96 |
| 2019 | 3 | 3,421 | $64.98 | $59.42 |
| 2018 | 1 | 140 | $65.00 | $66.44 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 20, 2023 | 61J04 | CookDistrict 1 | 2,265 CU YD | $48.00 | Plote Construction, Inc. |
| Apr 26, 2019 | 61F09 | CookDistrict 1 | 1,907 CU YD | $75.00 | R. W. Dunteman Company |
| Apr 26, 2019 | 61F10 | CookDistrict 1 | 935 CU YD | $60.00 | R. W. Dunteman Company |
| Jan 18, 2019 | 61F00 | CookDistrict 1 | 579 CU YD | $40.00 | Plote Construction, Inc. |
| Aug 3, 2018 | 61E16 | CookDistrict 1 | 140 CU YD | $65.00 | Plote Construction, Inc. |