$111.51Avg low bid / FOOT
$108.10Avg of all bids
—Avg engineer's estimate
5Jobs · 905 FOOT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2025 | 1 | 177 | $122.26 | $142.82 |
| 2022 | 1 | 277 | $125.00 | $119.51 |
| 2021 | 2 | 414 | $85.52 | $91.26 |
| 2018 | 1 | 37 | $250.00 | $231.40 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 17, 2025 | 61K68 | KaneDistrict 1 | 177 FOOT | $122.26 | Martam Construction Incorporated |
| Mar 11, 2022 | 61H14 | CookDistrict 1 | 277 FOOT | $125.00 | Plote Construction, Inc. |
| Apr 23, 2021 | 61G58 | KaneDistrict 1 | 404 FOOT | $86.00 | Martam Construction Incorporated |
| Mar 5, 2021 | 62J27 | CookDistrict 1 | 10 FOOT | $66.00 | Lorig Construction Company |
| Jun 15, 2018 | 60W53 | CookDistrict 1 | 37 FOOT | $250.00 | D. Construction, Inc. |