$2,030.18Avg low bid / EACH
$2,243.03Avg of all bids
—Avg engineer's estimate
4Jobs · 28 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2022 | 1 | 2 | $4,700.00 | $5,901.27 |
| 2020 | 1 | 11 | $1,460.00 | $1,626.67 |
| 2018 | 2 | 15 | $2,092.33 | $2,095.37 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 5, 2022 | 61H87 | CookDistrict 1 | 2 EACH | $4,700.00 | Copenhaver Construction, Inc. |
| Jun 12, 2020 | 60X94 | CookDistrict 1 | 11 EACH | $1,460.00 | Lorig Construction Company |
| Nov 9, 2018 | 60X93 | CookDistrict 1 | 10 EACH | $2,626.00 | James McHugh Construction Co. |
| Jan 19, 2018 | 61E28 | LakeDistrict 1 | 5 EACH | $1,025.00 | Lorig Construction Company |