$5.25Avg low bid / SQ YD
$5.19Avg of all bids
—Avg engineer's estimate
10Jobs · 188,676 SQ YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 30,471 | $5.00 | $5.00 |
| 2023 | 3 | 152,074 | $5.12 | $5.10 |
| 2022 | 1 | 370 | $8.00 | $8.67 |
| 2021 | 1 | 381 | $10.00 | $16.25 |
| 2019 | 2 | 4,826 | $9.17 | $8.33 |
| 2018 | 2 | 554 | $12.88 | $11.10 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Mar 8, 2024 | 60R49 | CookDistrict 1 | 30,471 SQ YD | $5.00 | R. W. Dunteman Company |
| Sep 22, 2023 | 62R29 | WillDistrict 1 | 151,258 SQ YD | $5.06 | D. Construction, Inc. |
| Jun 16, 2023 | 62G37 | CookDistrict 1 | 333 SQ YD | $20.00 | K-Five Construction Corporation |
| Jun 16, 2023 | 62H82 | CookDistrict 1 | 483 SQ YD | $15.00 | Judlau Contracting, Inc. |
| Jun 17, 2022 | 62H15 | WillDistrict 1 | 370 SQ YD | $8.00 | D. Construction, Inc. |
| Nov 5, 2021 | 62C25 | CookDistrict 1 | 381 SQ YD | $10.00 | K-Five Construction Corporation |
| Apr 26, 2019 | 60T21 | KaneDistrict 1 | 781 SQ YD | $16.50 | D. Construction, Inc. |
| Mar 8, 2019 | 61F41 | CookDistrict 1 | 4,045 SQ YD | $7.75 | Plote Construction, Inc. |
| Aug 3, 2018 | 60P66 | KaneDistrict 1 | 149 SQ YD | $12.00 | Martam Construction Incorporated |
| Jan 19, 2018 | 60Y25 | CookDistrict 1 | 405 SQ YD | $13.20 | D. Construction, Inc. |