$275,833.33Avg low bid / L SUM
$421,637.15Avg of all bids
—Avg engineer's estimate
6Jobs · 6 L SUM
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2020 | 3 | 3 | $450,000.00 | $592,694.77 |
| 2019 | 1 | 1 | $25,000.00 | $25,000.00 |
| 2018 | 2 | 2 | $140,000.00 | $322,637.38 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2020 | 60X94 | CookDistrict 1 | 1 L SUM | $50,000.00 | Lorig Construction Company |
| Apr 24, 2020 | 62A76 | CookDistrict 1 | 1 L SUM | $900,000.00 | Lorig Construction Company |
| Apr 24, 2020 | 62A77 | CookDistrict 1 | 1 L SUM | $400,000.00 | Lorig Construction Company |
| Nov 8, 2019 | 62J31 | CookDistrict 1 | 1 L SUM | $25,000.00 | Lorig Construction Company |
| Nov 9, 2018 | 60X79 | CookDistrict 1 | 1 L SUM | $130,000.00 | James McHugh Construction Co. |
| Nov 9, 2018 | 60X93 | CookDistrict 1 | 1 L SUM | $150,000.00 | James McHugh Construction Co. |