$562.04Avg low bid / EACH
$598.34Avg of all bids
—Avg engineer's estimate
12Jobs · 158 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 8 | $316.00 | $426.75 |
| 2023 | 2 | 33 | $502.39 | $498.34 |
| 2022 | 2 | 80 | $563.46 | $698.95 |
| 2021 | 2 | 13 | $447.75 | $491.95 |
| 2020 | 3 | 14 | $1,018.11 | $717.14 |
| 2018 | 2 | 10 | $454.50 | $471.03 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 20, 2024 | 61K06 | CookDistrict 1 | 8 EACH | $316.00 | Martam Construction Incorporated |
| Jun 16, 2023 | 62G37 | CookDistrict 1 | 16 EACH | $570.00 | K-Five Construction Corporation |
| Mar 10, 2023 | 60Y72 | CookDistrict 1 | 17 EACH | $438.75 | Judlau Contracting, Inc. |
| Apr 29, 2022 | 62P45 | CookDistrict 1 | 9 EACH | $575.00 | Judlau Contracting, Inc. |
| Apr 29, 2022 | 64J65 | Rock IslandDistrict 2 | 71 EACH | $562.00 | McCarthy Improvement Company |
| Jun 11, 2021 | 64H08 | WinnebagoDistrict 2 | 9 EACH | $420.09 | William Charles Construction Company, LLC |
| Apr 23, 2021 | 61G58 | KaneDistrict 1 | 4 EACH | $510.00 | Martam Construction Incorporated |
| Nov 6, 2020 | 61G45 | CookDistrict 1 | 5 EACH | $467.50 | D. Construction, Inc. |
| Sep 18, 2020 | 60Y23 | CookDistrict 1 | 6 EACH | $511.00 | Alliance Contractors, Inc. |
| Jul 31, 2020 | 99639 | JacksonDistrict 9 | 3 EACH | $2,950.00 | Samron Midwest Contracting, Inc. |
| Aug 3, 2018 | 61E95 | CookDistrict 1 | 5 EACH | $444.00 | Iroquois Paving Corporation |
| Jun 15, 2018 | 60T01 | MchenryDistrict 1 | 5 EACH | $465.00 | Berger Excavating Contractors, Inc. |
| Apr 27, 2018 | 60T75 | LakeDistrict 1 | 19 EACH | $450.00 | Berger Excavating Contractors, Inc. |
| Apr 27, 2018 | 61E40 | DupageDistrict 1 | 1 EACH | $770.00 | D. Construction, Inc. |