Bid code AR752415

PRECAST REINFORCED CONC. FES 15" · per EACH

‹ All bid codes

$1,128.33Avg low bid / EACH
$1,017.22Avg of all bids
—Avg engineer's estimate
3Jobs · 12 EACH

Average low bid by year

YearJobsQuantityAvg lowAvg all
202012$1,140.00$962.50
201914$1,315.00$1,057.50
201816$1,000.00$1,000.00

Recent low bids

ExcelCSV
Let dateContractCounty / DistrictQuantityUnit priceLow bidder
Apr 24, 2020VA021 FayetteDistrict 72 EACH $1,140.00Stutz Excavating, Inc.
Jan 18, 2019KA048 KankakeeDistrict 34 EACH $1,315.00Kankakee Valley Construction Company, Inc.
Mar 9, 2018IL032 LasalleDistrict 36 EACH $1,000.00Advanced Asphalt Company