$85.66Avg low bid / EACH
$95.64Avg of all bids
—Avg engineer's estimate
2Jobs · 38 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2020 | 1 | 5 | $90.00 | $205.73 |
| 2019 | 1 | 33 | $85.00 | $76.19 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 31, 2020 | 61F92 | CookDistrict 1 | 5 EACH | $90.00 | Copenhaver Construction, Inc. |
| Jun 14, 2019 | 61E01 | KaneDistrict 1 | 33 EACH | $85.00 | Martam Construction Incorporated |