$3,630.71Avg low bid / EACH
$3,308.13Avg of all bids
—Avg engineer's estimate
11Jobs · 235 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 4 | 54 | $4,997.38 | $4,843.40 |
| 2022 | 1 | 46 | $4,914.00 | $5,075.94 |
| 2021 | 3 | 38 | $3,087.26 | $2,858.80 |
| 2019 | 2 | 49 | $2,550.82 | $2,636.33 |
| 2018 | 1 | 48 | $2,396.00 | $2,706.15 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 22, 2023 | 61H30 | CookDistrict 1 | 5 EACH | $6,435.00 | D. Construction, Inc. |
| Jun 16, 2023 | 61H85 | KaneDistrict 1 | 26 EACH | $5,310.91 | R. W. Dunteman Company |
| Jun 16, 2023 | 61J09 | CookDistrict 1 | 4 EACH | $4,950.00 | R. W. Dunteman Company |
| Jan 20, 2023 | 61J04 | CookDistrict 1 | 19 EACH | $4,200.00 | Plote Construction, Inc. |
| Jun 17, 2022 | 61H44 | CookDistrict 1 | 46 EACH | $4,914.00 | Alliance Contractors, Inc. |
| Jun 11, 2021 | 64H08 | WinnebagoDistrict 2 | 3 EACH | $6,938.65 | William Charles Construction Company, LLC |
| Apr 23, 2021 | 61G58 | KaneDistrict 1 | 25 EACH | $2,650.00 | Martam Construction Incorporated |
| Jan 15, 2021 | 61G83 | KaneDistrict 1 | 10 EACH | $3,025.00 | A Lamp Concrete Contractors, Inc. |
| Mar 8, 2019 | 61F57 | KaneDistrict 1 | 8 EACH | $2,350.00 | Curran Contracting Company |
| Jan 18, 2019 | 61F00 | CookDistrict 1 | 41 EACH | $2,590.00 | Plote Construction, Inc. |
| Aug 3, 2018 | 61E16 | CookDistrict 1 | 48 EACH | $2,396.00 | Plote Construction, Inc. |