$3.05Avg low bid / SQ FT
$3.80Avg of all bids
—Avg engineer's estimate
10Jobs · 83,925 SQ FT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 2,985 | $5.00 | $5.17 |
| 2022 | 2 | 23,232 | $2.81 | $2.95 |
| 2021 | 1 | 86 | $10.50 | $18.50 |
| 2020 | 2 | 11,208 | $3.90 | $3.79 |
| 2019 | 1 | 21,420 | $2.25 | $3.86 |
| 2018 | 3 | 24,994 | $3.32 | $5.03 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 19, 2024 | 62R89 | WillDistrict 1 | 2,985 SQ FT | $5.00 | Walsh Construction Company II, LLC |
| Nov 18, 2022 | 61H20 | WillDistrict 1 | 1,483 SQ FT | $2.30 | Austin Tyler Construction, Inc. |
| Mar 11, 2022 | 62D30 | CookDistrict 1 | 21,749 SQ FT | $2.85 | Alliance Contractors, Inc. |
| Mar 5, 2021 | 62L93 | CookDistrict 1 | 86 SQ FT | $10.50 | Builders Paving, LLC |
| Apr 24, 2020 | 62A76 | CookDistrict 1 | 175 SQ FT | $10.04 | Lorig Construction Company |
| Mar 6, 2020 | 60T05 | CookDistrict 1 | 11,033 SQ FT | $3.80 | Acura Inc. |
| Jan 18, 2019 | 62F23 | CookDistrict 1 | 21,420 SQ FT | $2.25 | J. A. Johnson Paving Company |
| Nov 9, 2018 | 60X79 | CookDistrict 1 | 2,933 SQ FT | $7.00 | James McHugh Construction Co. |
| Jun 15, 2018 | 62C74 | LakeDistrict 1 | 500 SQ FT | $6.25 | Peter Baker & Son Co. |
| Jun 15, 2018 | 68D69 | TazewellDistrict 4 | 21,561 SQ FT | $2.75 | Advanced Asphalt Company |
| Apr 27, 2018 | 62C17 | KaneDistrict 1 | 1,674 SQ FT | $3.25 | Lorig Construction Company |
| Jan 19, 2018 | 61E20 | CookDistrict 1 | 2,232 SQ FT | $2.50 | Davis Concrete Construction Co. |