$1,783.55Avg low bid / EACH
$2,106.53Avg of all bids
—Avg engineer's estimate
7Jobs · 11 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 3 | 5 | $2,095.00 | $2,442.67 |
| 2019 | 2 | 2 | $1,272.00 | $1,287.60 |
| 2018 | 2 | 4 | $1,650.00 | $1,793.73 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 8, 2024 | 61K59 | CookDistrict 1 | 3 EACH | $2,125.00 | A Lamp Concrete Contractors, Inc. |
| Aug 2, 2024 | 61J93 | MchenryDistrict 1 | 1 EACH | $2,500.00 | Plote Construction Inc. and Dunnet Bay Construction Company JV |
| Apr 26, 2024 | 61D34 | WillDistrict 1 | 1 EACH | $1,600.00 | D. Construction, Inc. |
| Nov 8, 2019 | 62F95 | CookDistrict 1 | 1 EACH | $1,294.00 | Kenny Construction Company_DO NOT USE |
| Apr 26, 2019 | 62H12 | CookDistrict 1 | 1 EACH | $1,250.00 | Arrow Road Construction Co. |
| Aug 3, 2018 | 61E17 | LakeDistrict 1 | 1 EACH | $1,800.00 | A Lamp Concrete Contractors, Inc. |
| Jun 15, 2018 | 61E53 | MchenryDistrict 1 | 3 EACH | $1,600.00 | Plote Construction, Inc. |